I changed the setting that allow to move computer activities in to different tasks. The result of this was terrible. Time consumed is no longer between task end minus task start calculation. With this setting "Time" is not affected by editing the start and stop time.
There should be a clean up function scanning for difference in "Time" and stamp duration.
Display lines in a report with possibility to correct "Time" to the time spent between start and stop.
Clean up / Check data suggestion
Anonymous
2020-02-21 08:02
Has the answer
Hello! If the option "Synchronise timeframe with duration when editing time entry:" is off, the time is not calculated automatically - it is working like that. You can put the number manually, or turn this feature on to get the right duration of your entries.
Who voted:
+ 2
Anonymous
Comments
j.krason
2020-03-12 16:16